A 47.9-metre Trinity, built 2004, taken back to substrate across paint, systems, joinery and exterior living areas — and handed back in nine months, to the day agreed at contract.
47.9 mLENGTH OVERALL9MONTHS IN YARD2004TRINITY YACHTSR15PROJECT CODE
Four trades, one winter, one fixed date.
Mirabella arrived in Tuzla in mid-September 2025 and was hauled out in early October. Paint, electrical and electronic systems, interior joinery and structural work on the transom all ran inside the same winter — against a redelivery date of 15 July 2026 fixed at contract signature and held to.
Rob Dolling of Verpeka Dolling Superyachts acted throughout as Owner's Representative and Owner's Technical Manager, carrying responsibility for quality, technical integrity and the date. R15 is the fifteenth major refit the yard has taken on since 2017, and among the widest in scope.
MID-SEPTEMBER 2025Arrival, TuzlaAlongside for survey and scope confirmation against the contract package.
EARLY OCTOBER 2025Hauled outOut of the water for paint preparation, transom work and running gear.
WINTER 2025–26Four trades in parallelPaint, electrical and electronics, joinery and structural work run at once, not in series.
15 JULY 2026RedeliveredThe date agreed at contract signature, held to across the whole programme.
BEFORE & AFTER — FROM ABOVE
Nine months apart, from the same height.
DRAG THE HANDLE
AFTER · JULY 2026
BEFORE · OCTOBER 2025
↔
Decks stripped back and covered while she lay in the floating dock, against the same decks finished: new teak, the sundeck Jacuzzi, awnings and tenders back aboard.
New railings, new entrance glass, an engraved family crest and a redrawn name and logo were produced and fitted in-house, so the details match the new finish rather than survive it.
WHERE THE WORK SHOWS
Move the line. Open a marker.
DRAG THE HANDLE · OPEN THE MARKERS
BEFORE
AFTER
↔
INTERIOR
TV-lift and ceiling integration
A TV-lift fitted with the structural work it demanded, ceiling panels reworked around the mechanism, and the whole assembly folded into the yacht's automation.
CEILINGS
Ceilings, entirely renewed
Every ceiling panel replaced and redesigned around teak frames with stainless finishes, and the old Velcro fixings retired for a fast-mount system that comes down cleanly for service.
ACCESS
New automatic sliding door
The manual one-metre door gave way to a 3.5-metre automatic opening — structural and interior work carried together, so the saloon now reads as one room with the aft deck.
FURNITURE
Sibennesse, built to the deck
Sibennesse pieces custom-designed and built in Germany, then set into the new deck layout so the furniture and the design philosophy arrive as one decision rather than two.
GLASS
New glass manufactured and incorporated
New glass drawn and manufactured specifically for this deck, shielding the aft seating from the breeze without closing the view down.
SURFACES
Marble, bordered in teak
New marble custom-designed and set within teak borders, and a new sink dropped in so its teak cover closes flush with the counter — no lip, no seam to catch.
AFT SEATING
A seating group, redesigned and rebuilt
The aft seating group drawn again and built new — a marble surface set into it, a planter closing the back, and every cushion reupholstered to the new scheme.
LIGHTING & POWER
New lighting system
A new automated LED lighting system throughout, and the whole yacht converted from American to European voltage — the change you never see, felt in every switch.
TEAK
New deck, laid to 15 mm
The teak lifted and replaced in full, laid at 15 mm to match the decking thickness carried elsewhere onboard — one plane, one standard, throughout.
ENTRY
A door with the family crest
A new stainless steel door, custom made with laminated glass and the family crest engraved into it — the last thing built and the first thing anyone touches.
THE ALBUM
Every frame we kept.
85 PHOTOGRAPHS
THE WORK, IN DETAILFOUR DISCIPLINES, ONE WINTER
01
Paint & structure
HULL · SUPERSTRUCTURE · TRANSOM
Hull and superstructure were stripped and fully repainted in climate-controlled conditions — the change that resets how a 2004 aluminium hull reads on the water. In the same programme the transom area was structurally revised to take an integrated transformer at the swim platform, with a dedicated watertight chamber built to house it.
Full exterior repaint of hull and superstructureClimate-controlled preparation and applicationStructural revision to the transom areaDedicated watertight chamber for the transformerNew railings, new entrance glass, engraved family crestLogo and name design, production and installation
02
Systems & light
ELECTRICAL · ELECTRONICS · MECHANICAL
The electrical and electronic infrastructure was substantially renewed — audio-visual systems, bridge electronics, and a complete rethink of interior lighting alongside significantly enhanced exterior deck lighting. Mechanical work ran in parallel: stabiliser overhaul, main engine maintenance and replacement of the generator exhaust outlet scoop.
Electrical and electronic infrastructure renewedAV systems and bridge electronicsInterior lighting redesignedExterior deck lighting significantly enhancedStabiliser overhaul; main engine maintenanceGenerator exhaust outlet scoop replaced
03
Joinery & interior
VENEER · UPHOLSTERY · MARBLE
Twenty-two years of sun, salt and humidity had dulled the varnished joinery to a cloudy haze. The affected veneers were taken back to bare wood, sanded, and re-finished in a new walnut — chocolate tone under controlled conditions: a deliberately labour-intensive route chosen to preserve the character of Scott Carpenter's original interior rather than mask it.
Varnished woodwork stripped, sanded and re-finished throughoutNew walnut — chocolate toneNew upholstery; furniture refreshed or replacedInterior floor replacement and marble installationComplete galley renewal
04
Deck & exterior living
SUNDECK · SEATING · TEAK
The most visible changes are on deck. A bespoke Jacuzzi was installed on a redesigned sundeck, new exterior seating areas were created across all decks, and exterior marble was replaced with a teak border. Teak renewals ran across the yacht, so the surfaces underfoot match the standard of the repaint above them.
Bespoke Jacuzzi on a redesigned sundeckNew exterior seating areas across all decksExterior marble replacement with teak borderTeak renewalsSwim platform reconfigured with integrated transformer
“You can judge a yard by what it takes on in one winter. R15 asked for paint, systems, joinery and structural work at once, to a date we had committed to, and our people carried all four across the line together. Mirabella left Tuzla genuinely transformed — that is why Reviva exists.”
RAMAZAN MENGIREFIT OPERATIONS, REVIVA / MENGI YAY
“The scope on Mirabella touched almost every technical discipline onboard simultaneously. Mengi Yay's direct access to specialised trade resources — from marine electrical and mechanical teams to interior joiners — allowed us to address a wide range of complex works within a single winter period.”
ROB DOLLINGVERPEKA DOLLING SUPERYACHTS · OWNER'S REPRESENTATIVE & TECHNICAL MANAGER
Scope of works, as delivered.
01Full exterior repaint of hull and superstructure in climate-controlled conditions02Renewal of electrical and electronic infrastructure, including AV and bridge systems03Redesigned interior lighting and substantially enhanced exterior deck lighting04Varnished woodwork stripped, sanded and re-finished throughout the interior05Mechanical overhaul: stabiliser overhaul, main engine maintenance, generator exhaust scoop replaced06New upholstery; furniture refreshed or replaced across guest and owner areas07Bespoke Jacuzzi installed on a redesigned sundeck08Logo and name design, production and installation09Interior floor replacement and marble installation10Exterior marble replacement with teak border11New railings, new entrance glass and family crest logo engraving12Complete galley renewal13Teak renewals14New exterior seating areas created across all decks15Swim platform reconfigured with integrated transformer, structural revision to the transom and a dedicated watertight chamber
Key specifications
She accommodates eleven guests across five staterooms — four with king berths, one twin with a Pullman — and carries a crew of nine. Mirabella now returns to the Mediterranean.
A 47.9-metre Trinity, built 2004, taken back to substrate across paint, systems, joinery and exterior living areas — and handed back in nine months, to the day agreed at contract.
{{ h.v }}{{ h.k }}
Four trades, one winter, one fixed date.
Mirabella arrived in Tuzla in mid-September 2025 and was hauled out in early October. Paint, electrical and electronic systems, interior joinery and structural work on the transom all ran inside the same winter — against a redelivery date of 15 July 2026 fixed at contract signature and held to.
Rob Dolling of Verpeka Dolling Superyachts acted throughout as Owner's Representative and Owner's Technical Manager, carrying responsibility for quality, technical integrity and the date. R15 is the fifteenth major refit the yard has taken on since 2017, and among the widest in scope.
{{ t.when }}{{ t.what }}{{ t.note }}
BEFORE & AFTER — FROM ABOVE
Nine months apart, from the same height.
DRAG THE HANDLE
AFTER · JULY 2026
BEFORE · OCTOBER 2025
↔
Decks stripped back and covered while she lay in the floating dock, against the same decks finished: new teak, the sundeck Jacuzzi, awnings and tenders back aboard.
New railings, new entrance glass, an engraved family crest and a redrawn name and logo were produced and fitted in-house, so the details match the new finish rather than survive it.
{{ frameLabel }}{{ room.name }}
AFTER
BEFORE
↔
{{ room.body }}
{{ w.t }}
{{ albumName }} — ALL FRAMES
WHERE THE WORK SHOWS
Move the line. Open a marker.
DRAG THE HANDLE · OPEN THE MARKERS
BEFORE
AFTER
↔
INTERIOR
TV-lift and ceiling integration
A TV-lift fitted with the structural work it demanded, ceiling panels reworked around the mechanism, and the whole assembly folded into the yacht's automation.
CEILINGS
Ceilings, entirely renewed
Every ceiling panel replaced and redesigned around teak frames with stainless finishes, and the old Velcro fixings retired for a fast-mount system that comes down cleanly for service.
ACCESS
New automatic sliding door
The manual one-metre door gave way to a 3.5-metre automatic opening — structural and interior work carried together, so the saloon now reads as one room with the aft deck.
FURNITURE
Sibennesse, built to the deck
Sibennesse pieces custom-designed and built in Germany, then set into the new deck layout so the furniture and the design philosophy arrive as one decision rather than two.
GLASS
New glass manufactured and incorporated
New glass drawn and manufactured specifically for this deck, shielding the aft seating from the breeze without closing the view down.
SURFACES
Marble, bordered in teak
New marble custom-designed and set within teak borders, and a new sink dropped in so its teak cover closes flush with the counter — no lip, no seam to catch.
AFT SEATING
A seating group, redesigned and rebuilt
The aft seating group drawn again and built new — a marble surface set into it, a planter closing the back, and every cushion reupholstered to the new scheme.
LIGHTING & POWER
New lighting system
A new automated LED lighting system throughout, and the whole yacht converted from American to European voltage — the change you never see, felt in every switch.
TEAK
New deck, laid to 15 mm
The teak lifted and replaced in full, laid at 15 mm to match the decking thickness carried elsewhere onboard — one plane, one standard, throughout.
ENTRY
A door with the family crest
A new stainless steel door, custom made with laminated glass and the family crest engraved into it — the last thing built and the first thing anyone touches.
THE ALBUM
Every frame we kept.
85 PHOTOGRAPHS
THE WORK, IN DETAILFOUR DISCIPLINES, ONE WINTER
{{ c.num }}
{{ c.name }}
{{ c.tag }}
{{ c.body }}
{{ it.t }}
{{ q.text }}
{{ q.who }}{{ q.role }}
Scope of works, as delivered.
{{ s.n }}{{ s.t }}
Key specifications
She accommodates eleven guests across five staterooms — four with king berths, one twin with a Pullman — and carries a crew of nine. Mirabella now returns to the Mediterranean.