IV — THE FLEET · IN THE YARD
ONE PROGRAMME ON THE FLOOR · AUGUST 2026
Work in progress
One programme is running on the floor this month: a complete set of steel sailing masts for the 1931 four-masted barque Sea Cloud, built here and shipped to Malta to be stepped aboard. The scope, the stage and the dates are published; the rest stays with her owner.
SCROLL
THE SCHEDULE
One programme across twenty-four months.
Solid is work booked and running. Dashed is planned, and moves only in writing — with the owner's representative in the room.
2026 Q1
Q2
Q3
Q4
2027 Q1
Q2
Q3
Q4
TODAY · AUG 2026
SPRING 2027
43 M · DRY DOCK
WINTER 2026
40 M · SHED TWO
R18
AUTUMN 2027
109.93 M · HARDSTANDING
18
IN FABRICATION · DNV CLASS
MAST SHOP · YARD CODE R18
A square rig, built new in steel.
The complete set of sailing masts for the 1931 four-masted barque Sea Cloud, built in steel as the originals were — heavier sections, tighter distortion control and a far more demanding approach to alignment than a modern spar would ask for. Fabrication runs in full at Tuzla; the finished masts are sea-fastened and shipped to Malta to be stepped aboard.
Certified steel procured, traceable to class
COMPLETE
Tapered mast sections rolled, formed and welded
UNDERWAY
Welds examined to the agreed NDT plan
SCHEDULED
Shop trial assembly, coating and sea-fastening
SCHEDULED
STATED COMPLETION
0%
FABRICATION BEGAN AUGUST 2026DELIVERY TO MALTA · DATE TO FOLLOW
MAST SECTIONS IN THE SHOP · TUZLA
EVERY FRIDAY
The week, photographed and written down.
Hours booked, work packages closed, variations raised — and the photographs to go with them. Owners and captains get the same file we do.